Cookie Policy, or visit our Privacy Notice page for more information on how we manage and use data.
Progress is well advanced on Lismore Comprehensive School with structural steelwork nearing completion and commencement of ground floor and first floor blockwork now that roof construction is underway. Drone footage provided by the School demonstrates the scale and complexity of the new build, particularly displayed in the school meals accommodation with curved foundations awaiting steel framework. Hockey and football pitch construction towards the east of the site are also progressing in preparation for the specialist 3G synthetic surface. Construction commenced in April 2021 and is due to complete by mid-2023.
McAdam and O’Hare & McGovern are currently working with Craigavon Area Foodbank to support those in need. More details can be found via their website